Reclamation of the Dergachiv landfill continues.

Currently, 2/3 of the retaining wall of the western slope of the landfill has been built, 29 gas wells have been drilled and equipped, and drilling and arrangement of the last six are planned to be completed within the next week.

The corner of the southern slope is being planned in accordance with the requirements of the DBN of Ukraine, next week it is planned to import a layer of soil and prepare for the laying of a gas pipe.

The eastern slope of the landfill is 90% ready for covering with a layer of soil.

Reclamation works are carried out in accordance with the work schedule.