April 16, 2021 A regular meeting was held in the office of the Consultant, KOKS, on the construction of a new landfill with the collection and disposal of landfill gas.

The issues of adherence to the work schedule were discussed, the Contractor reported that work is underway on concreting the floor of the sorting complex, laying insulation and roofing membrane.

Also internal works in an administrative and household building are carried out, works on installation of fire-prevention system and system of ventilation are planned to begin.