Work continues on the construction of a new landfill and sorting complex. The installation of an automatic fire extinguishing system, elements of the ventilation and heating system is currently underway.

Installation of sorting line structures, its conveyors and sorting cabins has also started.

These works are scheduled to be completed by the end of August.

At the same time, the territory around the waste processing complex is being arranged. The surface for asphalt is leveled and compacted.

There is an installation of a gas-supplying branch from a compressor station to gas-generating installations.

Gas supply and start-up of generators are planned for August.